Sample job

AHU-1, traced from sequence to code

A VAV AHU, economizer, pumped preheat, 2-stage direct evap, CHW coil, SF/RF on VFDs on a Distech ECY-S1000 + 2x ECY-8UI6UO-HOA, ECY-16DI, ECY-8DOR. Every control function below links back to the part of the sequence it implements. Open the files in EC-gfxProgram, Workbench and Excel and check them yourself.

29control functions
10RFI questions, with the assumption used
43hardware points
96points bound on the graphic

Traceability

Every function, traced

Grouped by the logic sheet it lives on, in the order the sheets appear in the program.

AHU-1 sequence of operations excerpts

Modes

Safeties

Fans

Discharge Air

Preheat

Economizer

Evaporative

Sump

Cooling Coil

Alarms

First deliverable

The RFI

Sent to the engineer of record before anything else. Each question carries the assumption the code is built on until it is answered, so the build doesn't wait.

  1. RFI-01Sequence A.2

    Optimal start: the sequence asks for Optimal Start-Stop but gives no limits. Confirm the BAS schedule is the source of occupancy and minutes-to-next-occupancy, and the maximum early start.

    Assumed: Distech OptimumStart (adaptive, learns min/degF factors) with the BAS schedule as source; maximum early start 120 min; warm-up / cool-down limited to the OA conditions in D.2 / D.3.

  2. RFI-02Sequence B.2

    Duct static high limit: "does not exceed 1.0 in. WC above scheduled total fan static / TAB value" - what absolute limit at PT-1 should be used?

    Assumed: 2.0 in.wc at PT-1 (adjustable) until TAB sets it.

  3. RFI-03Sequence B.2

    Duct static trim & respond parameters (initial, minimum, trim, respond, max respond, interval) are not given.

    Assumed: Initial 0.5, min 0.3, max 1.0 in.wc; trim 0.04, respond 0.06/request, max 0.15; 2 min interval; 2 ignored requests.

  4. RFI-04Sequence B.5

    PDAT reset range and trim & respond amounts are not given.

    Assumed: 55-65 F; trim +0.2 F, respond -0.3 F/request, max -1.0 F; starts at 65 F.

  5. RFI-05Sequence B.7

    Preheat setpoint clamp limits and the start-up ramp (span and duration) are not given.

    Assumed: Clamp 45-60 F; ramp starts 10 F high and steps down 1 F every 2 min (20 min) when OA < 40 F at start.

  6. RFI-06Sequence C.2, D.1

    "Minimum position vs. OA-T" for the preheat valve is not defined.

    Assumed: 0% at 35 F OA rising linearly to 30% at 0 F OA.

  7. RFI-07Sequence B.8, B.9

    Minimum OA airflow, CO2 maximum setpoint and the CO2-reset maximum airflow are not given.

    Assumed: Min OA 4,000 CFM; RA-CO2 limit 1,000 ppm; CO2 reset up to 8,000 CFM.

  8. RFI-08Sequence B.10

    Evap "call for cooling" and the stage 2 off condition are not defined; minimum on/off times are not given.

    Assumed: Call when MA-T > cooling setpoint + 2 F (off at setpoint); stage 2 off when EV-T < setpoint - 1 F; pumps 5 min on / 5 min off.

  9. RFI-09Sequence B.11, B.12

    Dry-out: confirm "ran >= 1 hr" may be one continuous hour, and what runs during dry-out (assumed fan on with OA at minimum, pumps off). Weekly drain day?

    Assumed: One continuous hour of stage 1 in the last 24 h; fan on, pumps off, MV-1 open on the weekly drain day from the BAS schedule.

  10. RFI-10Points list, M3-DI11/12

    Smoke detector auxiliary contact action (opens or closes on alarm) is not stated.

    Assumed: Closes on alarm (no reverse action on SA-SMK / RA-SMK).

Start a job like this